Home Construction Cost Breakup

Rates may vary as per Agreement

Booking Amount

5%

Design preparation, soil testing , site survey, material & contractor blocking.

Foundation work, footing casting & Plinth

20%

Casting of footings , Raising of columns to plinth level, consolidation of soil, casting of plinth beam and completing (M20 or M25) for below flooring within the plinth area.

Brick work

15%

Casting of footings , Raising of columns to plinth level, consolidation of soil, casting of plinth beam and completing (M20 or M25) for below flooring within the plinth area, sump top Construction of brick wall, casting of lintels, chajja.

Slab

23%

Casting of roof slab with shuttering, tying of steel for roof, electrical conduit laying, Casting of roof slab with shuttering, tying of steel for roof, electrical conduit laying.

Plastering work

10%

External / Internal plastering.

Flooring

5%

Fixing of tiles for bath rooms, Laying of granite or vitrified tiles for flooring in other areas.

Electrical & Plumbing

5%

Plumbing and Electrical works internal with laying of pipes.

Painting work

5%

Painting of internal and external wall with putty works for internal walls, exterior emulsion painting, all finishing.

Wood work and railing work

5%

Carpentry works of all doors and windows, Fabrication of railings.

Interior

5%

Interior woodwork as per the design.

Handover

2%

Final handover